# LCMS Convention Proceedings_St. Louis Missouri_1884_S33 # AI translation — CHI Digital Archive (demonstration) Fourth Delegate Synod of Missouri, Ohio, and Other States. 1884. 33 was bound to result in a significant increase in building costs is obvious and needs no proof. "But the main reason the cost overrun escaped the committee's control was this: everyone knows that the first cost estimates for a building are more rough approximations than exact calculations. So it naturally was with our building as well. Had the committee, right after the plan was adopted, immediately obtained bids for the whole building, on the basis of which its construction could and would have proceeded, it would have seen in time that the costs of execution exceeded the approved sum by too much. The committee could then still have made sweeping changes. Instead, however, we were advised by many quite competent people not to give the whole building to a single contractor, but to let out the various contracts separately, as is also the general custom for all large buildings. This has the great advantage that the building material, as well as the workers and subcontractors, can be better supervised, and the percentage that a general contractor takes from subcontractors is saved. This was borne out in the course of the building as well. But the committee then faced the other unfortunate circumstance, that it could no longer go back or make significant changes once the later contracts showed how far the fixed sum was being exceeded in carrying out the plan that had been adopted. The Reverend Synod has, however, seen from the accounts of the General Treasurer that the sums given for the contracts named there, in Number 21 of the 'Lutheraner' for the year 1882, have not been exceeded but have in fact come in about $700 lower. — Of this the Reverend Synod may be assured, and may obtain the judgment of any expert it likes, that the solidity of the building, in both material and workmanship, leaves nothing to be desired. "But it might still be objected against the committee that it exceeded, without necessity, the fixed 10 percent for the exterior and interior ornamentation of the building. We answer: as regards the stonework, we are ready to plead guilty at once, though the committee could only properly judge, once the work stood finished, how much could have been saved on it. As for the marble slabs in the vestibules and in the washrooms, and the stained glass, however, these may appear more like luxury, but are in truth, in the long run, the cheapest because the most durable. Curtains or wooden shutters in the assembly hall would soon require ongoing repairs and, eventually, complete replacement. The stained glass continually serves its purpose and never needs costly repair or renewal. Indeed, nowadays not even the smallest church is built without better, or colored, glass in its windows." (Report of the Building Committee.)